HICC, A Major Force for the Construction of Medical and Health Facilities

Issuing time:2020-04-24 16:25



Since the outbreak of COVID-19, HICC has taken the initiative to undertake the construction and reconstruction tasks of nearly 20 special hospitals, including square cabin hospitals, and isolation places in Wuhan, Xiangyang, and Yichang, making positive contributions to win the epidemic prevention and control war and protecting people's lives and safety.

 

For a long time, the "102" iron armyreferring to HICCis an important force in medical and health construction which has been struggling on the front line to let the people receive better medical service.

 

Below, please take a look at the medical facilities contracted by HICC with you.

 

Taihe Hospital of Shiyan City

 

Taihe Hospital of Shiyan City is a third-grade class-A hospital whose inpatient department building was constructed by Hubei Construction Group Third Construction Engineering. The building was put into use in 1995. The number of inpatient beds has increased to 1,100. Now, Taihe Hospital has become a regional medical facility covering six cities of four provinces including Hubei, Henan, Shanxi and Sichuan.


Wudang Mountain Campus of Taihe Hospital of Shiyan City

 

In September of 2015, 20 years after the building of the inpatient department of Taihe hospital was built, the hospital cooperated with Hubei Construction Group Third Construction Engineering to build the Wudang Mountain Campus of Taihe hospital again.

In September 2015, the cornerstone laying ceremony for the Wudang mountain hospital area of Taihe hospital (photo)

 

Wudang mountain hospital area is located at the taiji lake under Wudang mountain, adjacent to the administrative Committee of Wudang mountain special zone. The first phase covers an area of over 66667 m2 and has 600 beds. It is a modern, garden-like and intelligent tertiary hospital. The hospital is an important measure to promote the balanced development of high-quality medical resources in Shiyan city, and is an important support to implement the regional and industrial layout of the city's "one center, two boosters and three pillars" and to turn Wudang mountain into the health and cultivation capital of the east.

 

      


On December 21, 2019, Wudang Mountain Hospital area of Taihe Hospital was officially opened.

 

Hainan Branch of 301 Hospital of PLA

 

In December of 2019, the parking lot project of Hainan Branch of PLA 301 Hospital constructed by HICC was put into use, which fundamentally solved the problem of insufficient public parking spaces in the hospital, elevated the level of public service and improved the surrounding environment of the hospital.

 

         


The project investment is about 122 million yuan, including the construction of 790 parking spaces with 750 underground parking spaces and 40 ground parking spaces. Later, according to the actual requirements, the underground parking spaces can be renewed and expanded into mechanical and three-dimensional garages which can increase the parking spaces greatly. A basement of full rooms is set underground. The ground bus stops are 441 square meters. The substation covers 132 square meters. The helicopter hangar is 748 square meters.

  

Wuchang Hospital

 

General ward building of Wuchang Hospital is located at the north side of the east district of Wuchang Hospital, No. 745, Heping avenue, Yangyuan street, Wuchang district, Wuhan city.  The general ward building has eleven floors with one basement. The total construction area is 14,000 square meters, which is constructed by HICC International Engineering Company. The total number of beds is 366, including 276 beds in the general ward (including 14 barrier-free beds), 14 beds in the coronary heart disease intensive care unit, 39 beds for kidney dialysis, and 37 newborn beds.

 

During the fight against the epidemic, Wuchang hospital played an important role as the designated treatment hospital. The director of the hospital, Liu Zhiming, fighting on the front line, unfortunately infected with the disease and died at his post. The project of general ward building is one of the important task that Director Liu was responsible for. It is a significant event in the history of Wuchang hospital. HICC project department will fulfill its mission, carry forward the spirit of the craftsman and build the hospital well. Serve the patients better and comfort the martyrs in heaven.

 

On Nov.28, 2018Liu Zhiming gave a speech at the project mobilization meeting

  

On Dec. 25, 2019  the concrete structure is completed

 

 

Hubei Cancer Hospital

 

The contract cost of Hubei Cancer Hospital’s logistic building is 79.2 million RMB. The project includes one floor underground and eight floors above ground with total construction area of 16700m2. It has a dining hall, laundry room, medical records room, apartment of interns and doctors etc. After the hospital is completed, it will become a crucial guarantee to promote the sustainable development of the hospital and building a harmonious and safe hospital.

 

 

Shouyi Campus of Wuhan Third Hospital

 

The contract costs of new Burn Clinic Building of Shouyi campus is 107 million RMB. The total construction area is 16,800 m2, the new building will be built at the same place where the old outpatient building is dismantled.

 

 

New Hospital area of Zigui County People's Hospital, Yichang

 

The project of Jinguangcheng district of Zigui County People's Hospital is located in Jinguangcheng New District of Zigui County,The total investment of the project is 485 million yuan, The planned bed number is 1000, including out-patient complex, emergency medical technology inpatient complex, infection department building, oxygen station, guards and other logistics auxiliary rooms.The total gross floor area is 119,500 m2.

 

 

 

            

 

The project will be designed according to the national second-class A and above general hospital construction standard. After completion, it will meet the needs of the county's medical and health development and the needs of the general public for medical treatment.

 

 

 

East Wind Peoples Hospital, Xiangyang

 

Xiangyang East Wind People's Hospital (City Integrated Chinese and Western Medicine Hospital) Complex Hospital building.The project is a key livelihood project in Xiangyang approved by Xiangyang.The Gross leasable area is nearly 43,000 m2, with 16 floors above ground and 1 floor underground, with more than 500 beds and a total investment of 180 million yuan. After the completion of the first phase of the project, the hospital will renovate the existing facilities such as the inpatient building (the second phase of the project) , the total number of beds will reach more than 800, and the overall size of the hospital at the end of the 13th Five-year Plan period will reach the Grade three level hospital.

  

 

On July 29, 2019, the main construction of the building was capped, and it is scheduled to be delivered by the end of 2020.

 

 

 

Chinese Medicine Hospital West Campus of Yunxi County

 

Yunxi County Chinese Medicine Hospital West Campus consists of three buildings, 1 #, 2 # and 3 #, referring to the inpatient building and the administrative office building. The total construction area covers 28,400 square meters. The hospital will be provided with 320 beds.

 

 

 

 

 

 

 

Chinese Medicine Hospital of Xinzhou District, Wuhan

 

Chinese Medicine Hospital of Xinzhou District, Wuhan is responsible for the TCM prevention, medical treatment, health care and rehabilitation of the people in the district. It is located at No.389 Qi’an Avenue, Xinzhou District. The inpatient building expansion project has been undertaken by HICC Third Company with a total construction area of 12,800 square meters, and it was delivered in 2019.

 

 

 

In the post-epidemic era, the need to build more scientific and reasonable public health facilities and improve the capacity of public health services is imminent. Enterprising, loyal and dedicated. HICC will inherit the “102” iron army spirits and continue to play a role in the construction of medical infrastructure, and lay a solid foundation for the high-quality development of medical and health services to better meet the health needs of the people.